Latest news

100 Avenue Road – Project Update

Please see below for a project update that was circulated to neighbours on the 25th July 2022. Dear Neighbour, I am writing with an update regarding Essential Living’s development at 100 Avenue Road, above Swiss Cottage Underground Station. Following an

Read More

Planning update: 19 January 2021

Camilla Lesser, Development Manager at Essential Living, said: “Essential Living is committed to delivering a high-quality new development at 100 Avenue Road and ensuring a positive and sustainable future for this accessible site. The principle of the development is established,

Read More

Construction Update: 8th Aug 2019

Progress over period (19/07/2019 – 08/08/2019) Structural demolition of existing ground floor slab On site crushing of hardcore resulted from demolition to minimise vehicle movement Breaking out existing foundations for piling works Installation of Temporary Works to support existing retaining

Read More

Construction Update: 14th May 2019

Demolition of level 05 to level 04 Scaffold removal from 2.4m above level 05 to 2.4m above level 04 Ongoing demolition of level 04 to level 03 concurrently with the scaffold removal around the perimeter Strip out works within the

Read More

Construction Update: 13th March 2019

Progress to date (11/03/19) LUL scaffold protection deck completed Site set up ongoing with the planned delivery of welfare cabins on 25/02/19 allowing JFH to release the ground floor area for service isolations, decommissioning and soft strip works to commence

Read More

Construction Update: 30th January 2019

Progress over period (17/01/2018 – 24/01/2019) Site Set up Erection of hoarding Limited ground clearance Scaffold erection Internal strip-out of buildings Actions over next period (24/01/2019 – 07/02/2019) Completion of hoarding Installation of additional environmental monitoring equipment and hoarding lighting

Read More