Construction Update: 30th January 2019

Progress over period (17/01/2018 – 24/01/2019)

  • Site Set up
  • Erection of hoarding
  • Limited ground clearance
  • Scaffold erection
  • Internal strip-out of buildings

Actions over next period (24/01/2019 – 07/02/2019)

  • Completion of hoarding
  • Installation of additional environmental monitoring equipment and hoarding lighting
  • Service isolations and M&E decommissioning continuing within the building
  • Continue scaffolding
  • Continue internal strip out
  • Commence demolition of single story restaurant building adjoining north block of main building. Building will be demolished using 20 tonne excavator with munching attachment that will be delivered to site on 02/02/2019