Construction Update: 14th May 2019

  • Demolition of level 05 to level 04
  • Scaffold removal from 2.4m above level 05 to 2.4m above level 04
  • Ongoing demolition of level 04 to level 03 concurrently with the scaffold removal around the perimeter
  • Strip out works within the basement area currently at 90%
  • Strip out works within the Ground Floor area currently at 90%