Construction Update: 13th March 2019

Progress to date (11/03/19)

  • LUL scaffold protection deck completed
  • Site set up ongoing with the planned delivery of welfare cabins on 25/02/19 allowing JFH to release the ground floor area for service isolations, decommissioning and soft strip works to commence
  • Hoarding erection completed, with 40% of the dibond cover already installed on the park side. Once trial pits are completed and hoarding re-instated to original design the north side of the hoarding will be mounted with new artwork
  • Scaffold erection ongoing and currently 60% complete
  • Soft strip out works at level 05, level 04, level 03 and level 02 completed. Level 01 currently at 35% complete whilst the basement is currently at 20% complete
  • Roof plant removal currently at 35% complete.